Author Topic: Waved releases  (Read 176 times)

Offline Matthias Veelaert

  • Newbie
  • *
  • Posts: 12
    • View Profile
Waved releases
« on: May 03, 2022, 03:31:55 AM »
Hi,

I have a quick question. Is it possible to release an application using waved releases?
For example, release the Citrix Workspace app to a test environment(so a group of users) and then automatically release this app 14 days later to the acceptance environment?

Thanks in advance!

Offline Adam Cook

  • Administrator
  • Full Member
  • *****
  • Posts: 108
  • Patch My PC Support
    • View Profile
Re: Waved releases
« Reply #1 on: May 03, 2022, 03:53:06 AM »
Yes, absolutely.

Using the right click option Manage assignments, you can designated AAD groups to be applied to newly uploaded packages and also configure the availability/deadline between each AAD group. This will allow you to create a phased/wave release of updates in a timely fashion.

Offline Matthias Veelaert

  • Newbie
  • *
  • Posts: 12
    • View Profile
Re: Waved releases
« Reply #2 on: May 03, 2022, 04:31:53 AM »
Perfect, Thanks!!